Bridge on river Skumbinit |
location |
Lushne - Albania |
design / construction year |
May 2000 / 2002 |
phase |
Detailed Design |
|
Constructive solution |
Bridging of the river Skumbinit (L=9*33=297,00 ì) |
- superstructure |
pre-stressed discontinuous construction - eleven girders in a cross section |
- substructure |
one expanded construction |
- middle piers |
reinforced concrete circular sections |
- end piers |
reinforced concrete sheets with parallel wings |
- foundations |
foundations on reinforced concrete posts |
- constrution technology |
mountable pre-stressed girders, erected with a horisontal crane |
- software |
CUBUS |
|
Working team: |
|
- Designers |
Emil Nikolov, Dimitar Popovski, Dragan Stamev - civ. eng. |
- Assistants |
E. Nineska, V. Arsovski - civ. tech.. |